Euston Mainline Station

Location: Euston Mainline Station

Duration: 18 months

Scope: Supply and fit to the new mezzanine to the main concourse station:

 

  • 1000m2 of particle board and fire rated enviroboard to new the mezzanine floor.
  • 1000m2 of double lined fire rated MF ceiling to the underside of the new mezzanine floor and the new retail units.
  • 1300m2 of SAS System 200 architectural ceiling.
  • 500 linear metres of plasterboard margin to juxtapose the SAS architectural ceiling.
  • 150m2 of fire compartmentalisation walls constructed to the new retail units.